Apply for an environment and planning permit
Are you planning to build or renovate? Do you want to change the use of a building, cut down a tree, put up an advertisement or install solar panels? Check first whether you need a permit. Afterwards you can submit your application.
How it works
You have a construction plan or other plan
Prepare your application well
Collect the documents
Apply
The municipality checks and reviews
You will receive a decision
After you apply
After you receive a permit, you still need to arrange a number of things. For example, you must report when the work starts. And a supervisor must inspect the work. You can find more extensive information about this step-by-step process on the page Begin link: Procedure after applying for environment and planning permit, end link..
Permit needed or not: Examples
No permit needed
For installing solar panels on buildings which are not in a Begin external link: protected area(External link), end external link..
Permit often needed
You often need a permit for these activities:
- Install solar panels on buildings in Begin external link: protected area(External link), end external link..
- Change the exterior of a building. For example, placing a signboard, roof structure, roof dormer, roof terrace, shed or fence or adding a garden.
- Change the interior of a building. For example, removing a load-bearing wall.
- Merge 2 or more living spaces into 1 home (Begin link: woningen samenvoegen, end link.).
- (Re)construct a building where you deviate from the Begin external link: rules in the Omgevingsplan(External link), end external link. (environmental plan). For example, extending a building into an area where construction is not normally allowed.
- Change the use of a building to deviate from the rules in the Omgevingsplan. For example, turning a residential home into a shop or office.
- Change a Begin link: municipal or national listed monument, end link..
- Display advertisements. For example, putting promotional stickers on windows, placing advertising signs or hanging ads on the building’s exterior.
- Begin link: Cut down, prune or replant trees, end link..
- Build or modify a driveway.
Permit always needed
You always need a permit to do the following work:
- Renovate a building in building in a Begin external link: protected area(External link), end external link..
- Build a Begin link: padel court, end link..
- Add a roof structure.
- Build a shed in the front garden.
Needed to apply
When you apply for an environment and planning permit in Omgevingsloket, you will see which documents you need to include.
If your plan does not meet the Omgevingsplan rules
Submit the following in addition with your application:
- clear information about the spatial impact of your plan. A spatial consultancy can assist you with this.
- a description of how you inform people in your area. This includes neighbours, local businesses and community organisations. You must do this before you apply for the permit.
Apply
Submit your application in the Omgevingsloket
Companies can log in with Begin link: eHerkenning, end link..
People can log in using DigiD. You do not have DigiD? Begin external link: Apply for DigiD(External link), end external link..
How long it takes
- The municipality usually makes a decision on your application within 8 weeks. It may extend this period once by a maximum of 6 weeks.
- Do you have a complex building plan? Then the municipality has 12 or 26 weeks to make a decision. You will receive a notification. The municipality may extend this period once by a maximum of 6 weeks.
Fees
The costs vary per building plan. The amount is at least € 180.85. Are you only changing the use of a building (for example, from residential to commercial)? Then the fee is € 500.75.
The total costs can run into several thousand euros depending on your plan and the situation. For large projects, the fee can be much higher. You can read more information in the Begin external link: Verordening leges Omgevingswet Den Haag 2024(External link), end external link. (in Dutch).
Good to know
Municipality will publish your application
The municipality will post an announcement about your application on Begin external link: Berichten over uw buurt(External link), end external link.. Anyone can view your application there or at Begin link: The Hague Information Centre, end link.. The construction drawings will also be made public.
Which information will not be made public?
- For example, applications that are important for security. Or for the protection of embassies and government organizations. Read the full rules in the Begin external link: Beleidsregel vertrouwelijke omgevingsvergunningen Den Haag 2019(External link), end external link. (in Dutch).
- If you request an initial ruling, only you will receive this. Other people cannot view or request it.
Inform your neighbours
- The municipality will also consider the interests of your neighbours. If you receive a permit, they have the right to file an objection.
- It is important to maintain good relations with your neighbours, especially if you are planning construction work. You can find tips on how to inform them on the page Begin link: Building in and with the neighbourhood, end link. (in Dutch).
Announce your building work
In a few special cases you must officially announce your plans before starting construction. For example, for the construction of a new detached house. Check the page Begin link: Melding Wet kwaliteitsborging, end link. (Wkb-melding) to see when this is required.
Include construction drawings
You must include construction drawings with every application. The municipality recommends working with a engineering design bureau or an architect. They can prepare the drawings for you. You can find the official requirements in the Begin external link: Environment Decree(External link), end external link. (Omgevingsbesluit).
Starting a business
- Have you found a building you want to use for your business? First, check in the Begin external link: Omgevingsplan(External link), end external link. whether this use is allowed for your type of business.
- If you want to use the building for a different type of business than what the Omgevingsplan allows, you can apply for an environment and planning permit to deviate from the rules.
Construction guidelines
Are you applying for an environment and planning permit involving a technical construction activity? If so, you must also pay attention to the structure of the building. For example, to ensure the safety, strength, and stability of the building. To do so, you must comply with the technical building regulations.
Read more about the rules below (in Dutch):
- IPLO: Begin external link: Omgevingsvergunning bij de technische bouwactiviteit(External link), end external link.
- Wetten.nl: Begin external link: Besluit bouwwerken leefomgeving (Bbl)(External link), end external link.
- Wetten.nl: Begin external link: Omgevingsregeling(External link), end external link.
Contact
Do you have any questions? Please Begin link: contact the municipality, end link..
Are you a business owner? Call 14070 to make an appointment at the Ondernemersportaal or visit the office at the Spui.