Dunne Bierkade: Work delayed

Published: 23 February 2018Modified: 23 February 2018

In mid-January work began on the last part of the Dunne Bierkade project. The work should have lasted 6 weeks but this was not feasible. The project manager now expects to be finished repaving the embankment in mid-March. Weather conditions could affect the end date.

The first trees have been replanted in the meantime. The rest will be planted in the coming weeks.

Street work

Due to the peaty ground the pavement could sink a bit. The municipality will keep an eye on this and will raise the pavement if that is necessary. This would take place outside the sidewalk cafe season.