Part 2 of work on Kijkduin-Houtrust route begins

Published: 8 May 2018Modified: 8 May 2018

The municipality will begin working on Part 2 of the roadworks on 7 May. The Machiel Vrijenhoeklaan will then close between the petrol station and De Savornin Lohmanlaan. The 1st part will remain closed. The intersection with the Muurbloemweg will be closed to motorised traffic. It will be accessible to pedestrians, cyclists and emergency service vehicles. The petrol station will remain accessible.

Sewage works and new road lay-out

The work will be carried out in this order:

  • The asphalt will be broken apart and removed.
  • The sewer pipes will be replaced.
  • The new lay-out of the road will be created. This will take place until 20 June. Between 20 June and 5 July no work will be carried out on the Kijkduin-Houtrust route during the Volvo Ocean Race. The route will be open to all traffic during this period.
  • The work on the intersection of the Daal en Bergselaan will be ready on 5 July. The intersection will then be open. This will be Part 3 of the project.

Information evening for work on the Segbroeklaan

In the 1st week of July 2018 Part 4 of the work on the Segbroeklaan will begin. Area residents will receive a letter from the municipality at the beginning of June with more information and an invitation for the information evening on 18 June.

Prepare in advance and follow the diversion routes.

Also see: www.kijkduinhoutrust.nl